Implementing Takt Planning and Takt Control Into Residential Construction

Joonas Lehtovaara, Iina Mustonen, Petteri Peuronen, Olli Seppänen, Antti Peltokorpi

Tutkimustuotos: Artikkeli kirjassa/konferenssijulkaisussaConference article in proceedingsScientificvertaisarvioitu

1076 Lataukset (Pure)

Abstrakti

This study addresses the suitability of takt planning and takt control (TPTC) for the interior phase in residential construction projects. The purpose is to gain understanding on how to best implement TPTC in residential construction. The study was conducted as a qualitative case study, by investigating TPTC implementation for the interior phase in a residential construction project in Finland. The initial motivation for takt implementation was to achieve better flow efficiency and radically shortened production duration. The analysis was based on 14 interviews, site observation, data from digital control tools and workshops, and aimed to identify lessons learned as well as required future development actions in TPTC implementation. The findings indicate that TPTC is well suitable for the interior phase and even in the first pilot project it substantially reduced the project duration. However, certain barriers, as well as enablers, were identified in both planning and control phases, which can be adopted as a basis for continuous development. For example, more detailed planning of wagons and tighter collaboration between all the project participants should be considered. The study represents the category of applied research and has implications for achieving the full potential of takt planning and control in the future.
AlkuperäiskieliEnglanti
OtsikkoProceedings of the 27th Annual Conference of the International Group for Lean Construction (IGLC)
JulkaisupaikkaDublin, Ireland
KustantajaInternational Group for Lean Construction (IGLC)
Sivut417-428
Sivumäärä12
DOI - pysyväislinkit
TilaJulkaistu - 2019
OKM-julkaisutyyppiA4 Artikkeli konferenssijulkaisussa
TapahtumaAnnual Conference of the International Group for Lean Construction - Dublin, Irlanti
Kesto: 1 heinäk. 20197 heinäk. 2019
Konferenssinumero: 27

Julkaisusarja

NimiAnnual Conference of the International Group for Lean Construction
KustantajaIGLC.net
ISSN (elektroninen)2309-0979

Conference

ConferenceAnnual Conference of the International Group for Lean Construction
LyhennettäIGLC
Maa/AlueIrlanti
KaupunkiDublin
Ajanjakso01/07/201907/07/2019

Sormenjälki

Sukella tutkimusaiheisiin 'Implementing Takt Planning and Takt Control Into Residential Construction'. Ne muodostavat yhdessä ainutlaatuisen sormenjäljen.

Siteeraa tätä