Design Process Stability: Observations of Batch Size, Throughput Time and Reliability in Design

Eelon Lappalainen*, Petteri Uusitalo, Olli Seppänen, Antti Peltokorpi

*Tämän työn vastaava kirjoittaja

Tutkimustuotos: Artikkeli kirjassa/konferenssijulkaisussaConference article in proceedingsScientificvertaisarvioitu

3 Sitaatiot (Scopus)
123 Lataukset (Pure)

Abstrakti

Despite recent developments in construction design management, too much variability still occurs in design processes. Batch size (BS) and throughput time (TT) reduction are recurring concepts in the lean construction literature related to the Last Planner© System (LPS). These three parameters are often used to reduce variability and improve flow and reliability in work processes. Some have attempted to reduce design variability through lean design management (LDM) and agile methods, but very few studies have analysed the interaction of these parameters in the design process. The purpose of this study is to investigate these variables and their interactions. Design process stability and reliability were measured over nearly two years in this study by using three parameters. According to the results, design teams with smaller BS’s of design tasks and higher percentages of planned tasks completed also had shorter design task TT’s. Designers may use these findings to improve their workflow monitoring and as a novel addition to LDM and coordination metrics.
AlkuperäiskieliEnglanti
Otsikko29th Annual Conference of the International Group for Lean Construction
KustantajaInternational Group for Lean Construction (IGLC)
Sivut605-612
Sivumäärä8
ISBN (elektroninen)9786124802546
DOI - pysyväislinkit
TilaJulkaistu - heinäk. 2021
OKM-julkaisutyyppiA4 Artikkeli konferenssijulkaisussa
TapahtumaAnnual Conference of the International Group for Lean Construction - Lima, Peru
Kesto: 14 heinäk. 202116 heinäk. 2021
Konferenssinumero: 29

Julkaisusarja

NimiAnnual Conference of the International Group for Lean Construction
KustantajaIGLC.net
ISSN (painettu)2309-0979

Conference

ConferenceAnnual Conference of the International Group for Lean Construction
LyhennettäIGLC
Maa/AluePeru
KaupunkiLima
Ajanjakso14/07/202116/07/2021

Sormenjälki

Sukella tutkimusaiheisiin 'Design Process Stability: Observations of Batch Size, Throughput Time and Reliability in Design'. Ne muodostavat yhdessä ainutlaatuisen sormenjäljen.

Siteeraa tätä