A new perspective of construction logistics and production control : An exploratory study

  • American University of Beirut

Tutkimustuotos: Artikkeli kirjassa/konferenssijulkaisussaConference article in proceedingsScientificvertaisarvioitu

38 Sitaatiot (Scopus)
1219 Lataukset (Pure)

Abstrakti

Construction logistics and production control can enhance project performance. Research addressing site material management mainly aims at reducing hauling distances and transportation costs. Other studies address the effects of logistics on labor productivity, proposing partial solutions instead of comprehensive optimization. Moreover, previous research on logistics optimization covers various stages of supply chain, but stops once materials reach the construction site. However, different techniques can be used to haul these materials from storage areas to workplaces, including push and just-in-time techniques. These methods along with the effects they can have on crew performance still need to be studied. Pull and push techniques have been studied and applied for production control purposes. However, zooming into the level of project locations, the effects of production control approaches on crew performance still need to be studied. This paper reviews onsite construction logistics and production control techniques, studies them at the level of locations, and proposes hypotheses to be evaluated in future research, relating logistics mechanisms and production control systems to productivity. This research is valuable due to exposing additional factors affecting labor productivity, and recommending further optimization in production planning and construction logistics.

AlkuperäiskieliEnglanti
OtsikkoIGLC 2018 - Proceedings of the 26th Annual Conference of the International Group for Lean Construction
AlaotsikkoEvolving Lean Construction Towards Mature Production Management Across Cultures and Frontiers
ToimittajatVicente A. Gonzalez
KustantajaInternational Group for Lean Construction (IGLC)
Sivut992-1001
Sivumäärä10
Vuosikerta2
ISBN (elektroninen)9789380689296
DOI - pysyväislinkit
TilaJulkaistu - 1 tammik. 2018
OKM-julkaisutyyppiA4 Artikkeli konferenssijulkaisussa
TapahtumaAnnual Conference of the International Group for Lean Construction - Chennai, Intia
Kesto: 16 heinäk. 201822 heinäk. 2018
Konferenssinumero: 26

Julkaisusarja

NimiAnnual Conference of the International Group for Lean Construction
KustantajaInternational Group for Lean Construction
ISSN (painettu)2309-0979

Conference

ConferenceAnnual Conference of the International Group for Lean Construction
LyhennettäIGLC
Maa/AlueIntia
KaupunkiChennai
Ajanjakso16/07/201822/07/2018

YK:n kestävän kehityksen tavoitteet

Tämä tuotos edistää seuraavia kestävän kehityksen tavoitteita:

  1. SDG 8 – Ihmisarvoinen työ ja taloudellinen kasvu
    SDG 8 – Ihmisarvoinen työ ja taloudellinen kasvu

Sormenjälki

Sukella tutkimusaiheisiin 'A new perspective of construction logistics and production control : An exploratory study'. Ne muodostavat yhdessä ainutlaatuisen sormenjäljen.

Siteeraa tätä