TY - GEN
T1 - Post-Fracture redundancy evaluation of a twin box-girder shinkansen bridge in Japan
AU - Lin, Weiwei
AU - Yoda, Teruhiko
AU - Taniguchi, Nozomu
AU - Lam, Heang
AU - Nakabayashi, Kazuki
PY - 2016/1/1
Y1 - 2016/1/1
N2 - As the national bridge inventory ages and traffic volumes increase, the government is spending more on maintaining their existing structures to extend the service life of the current bridge inventory. This includes two-girder bridges that are classified as fracture critical and non-redundant. Owing to the increased inspection costs associated with these fracture-critical bridges, there is a need to evaluate alternate load paths and to implement retrofit methods on existing bridge structures to avoid bridge replacement. In this paper, after-fracture redundancy of two-girder bridges is investigated through a case study for a four-span continuous steel-concrete composite twin boxgirder bridge. The finite element analysis was carried out to evaluate the load-carrying capacity after failure of one girder of the two-girder bridge. Two types of the main-girder damage, including fracture of the bottom flange only, and fracture of both bottom flange and the web were considered respectively in this study. Typical damage locations including mid-span section of the main girder and the sections near the intermediate support were also considered in the numerical analyses. On the basis of the numerical results, the present continuous steel-concrete composite box-girder bridge was classified as a redundant bridge, and the concrete deck was considered as the key member for ensuring the bridge redundancy after severe damages occurred on the main girders.
AB - As the national bridge inventory ages and traffic volumes increase, the government is spending more on maintaining their existing structures to extend the service life of the current bridge inventory. This includes two-girder bridges that are classified as fracture critical and non-redundant. Owing to the increased inspection costs associated with these fracture-critical bridges, there is a need to evaluate alternate load paths and to implement retrofit methods on existing bridge structures to avoid bridge replacement. In this paper, after-fracture redundancy of two-girder bridges is investigated through a case study for a four-span continuous steel-concrete composite twin boxgirder bridge. The finite element analysis was carried out to evaluate the load-carrying capacity after failure of one girder of the two-girder bridge. Two types of the main-girder damage, including fracture of the bottom flange only, and fracture of both bottom flange and the web were considered respectively in this study. Typical damage locations including mid-span section of the main girder and the sections near the intermediate support were also considered in the numerical analyses. On the basis of the numerical results, the present continuous steel-concrete composite box-girder bridge was classified as a redundant bridge, and the concrete deck was considered as the key member for ensuring the bridge redundancy after severe damages occurred on the main girders.
KW - FEM
KW - Field test
KW - Post-fracture
KW - Redundancy evaluation
KW - Twin box-girder
UR - http://www.scopus.com/inward/record.url?scp=84979642445&partnerID=8YFLogxK
M3 - Conference contribution
AN - SCOPUS:84979642445
T3 - IABSE Conference, Guangzhou 2016: Bridges and Structures Sustainability - Seeking Intelligent Solutions - Report
SP - 675
EP - 682
BT - IABSE Conference, Guangzhou 2016
T2 - IABSE Conference Guangzhou: Bridges and Structures Sustainability - Seeking Intelligent Solutions
Y2 - 8 May 2016 through 11 May 2016
ER -